The
Operations of the Cape Roberts Project
Summary:
Two key elements in the field operation
were a field camp for 40 people, set up just off Cape Roberts each September
and the 55 tonne drilling rig, set up 13 to 16 km offshore in early
October.
The sea ice on which the operation took place typically forms between April and June, and then thickens to around 2 m by early October. Water depths ranged from 122 m (CRP-1 )
to 295 m (CRP-3).
Once established the rig operated 24 hours a day, coring continuously with 97% recovery. The 12 hourly shift change was by helicopter from Marble Point or McMurdo Station.
Weather was mostly fine with light winds, with early season temperatures around -30ºC, rising to -5ºC by the conclusion of drilling in late November.
Operations during
set-up phase
Each season in late August
a group flew to Scott Base on WINFLY, and established a route on the new
sea ice north to Cape Roberts. They then located the site for the rig,
assembled the Cape Roberts Camp a few hundred metres north of the Cape on
the sea ice. At the end of September as the ice thickened to more than 1.5
m they towed out the 55 tonnes of drilling rig, drill pipe, and ancillary
buildings, and set these up at the drill site.
The
drilling system used for the Cape Roberts Project was a Longyear wireline Series
Q HD44 slim hole system commonly used for land-based mineral exploration. Thin
kerf diamond coring bits on the end of the drill rod are rotated at high speed
to drill the core, which is collected in a 3 or 6 m core barrel. The inner part
of the barrel containing the core is recovered with a wire line so that the
entire drill string is not removed each time core is recovered. This enables
coring at rates of 30 to 40 m/day and high quality core recovery.
Operations
at the drill site
Drilling
operations began with the cutting of a 1 m wide access hole in ice 1.6
to 2 m thick using a specially designed auger. The sea riser (SKETCH)
was then set up, and coring begun. Coring ended in 1997 on October 23 at
148 mbsf (by a storm-generated ice break-out), in 1998 on November 24 at
624 mbsf, and in 1999 on Nov 19 at 939 mbsf. During this time the rig
was operated continuously 24 hours a day with crews on 12 hour shifts.
The sea riser (see
diagram below) was
required to give lateral support to the drill rods in the water column
which are rotated at 600-1200 rpm for diamond coring and to provide a
return path for drilling fluid and cuttings. Modifications to the riser
system were carried out after the completion of the first hole (CRP-1 in
1997) which identified some shortcomings that would become critical in
the proposed deeper water sites. The modified riser system was used
successfully in both following seasons.
The
mud system is a very important part of the drilling operation because it
provides stability in the hole; control of downhole pressure and most
importantly increases core recovery and condition. The mud program used
was a non toxic biodegradable low solids system mixed from sea water
with potassium chloride (KCl) to increase the fluid density and natural
gum polymers to increase viscosity to keep cuttings in suspension so
that they can be cleared from the hole. The cuttings produced from
diamond coring were mostly fine sand, silt and clay. The sand and silt
were removed from the mud in a centrifuge with a processing capacity
down to 5 micron size particles before it was recirculated down the
hole.
|

|
|
Sea
riser |
Drilling
statistics for the Cape Roberts holes
|
Hole
|
CRP-1
|
CRP-2/2A
|
CRP-3
|
|
Location
|
77.008 S; 163.755 E
|
77.006 S; 163.719 E
|
77.011 S; 163.640 E
|
|
First core
|
17 October
|
16 October
|
9 October
|
|
Last core
|
24 October
|
25 November
|
19 November
|
|
Water depth
|
153 m
|
178 m
|
295 m
|
|
Depth to bottom of
hole
|
148 mbsf
|
624 mbsf
|
939 mbsf
|
|
Recovery
|
86%
|
94%
|
97%
|
Operations
at the Cape Roberts Camp
Cape Roberts
camp is home for up to 40 personnel during the drilling phase of the
operation. These include project manager, Jim Cowie, chief scientist,
Peter Barrett, the drilling team led by Pat Cooper, the core processing
team led by Alex Pyne, around 15 of the science team for core
measurements and description, and the camp support staff. Erecting
the camp on sea ice minimised impacts on Cape Roberts, only 7 hectares
in area, and provided easy access to the sea for water and waste
discharge.
Follow this link to see the core Cape
Roberts Camp Staff throughout the project.
Life was set
by the 12 hourly shift change at 0800 and 2000, which is effected by
helicopter. On just a few occasions each season bad weather forced the
shift change by Hagglunds tracked vehicle, the 23 km sea-ice road taking
around 50 bumpy minutes to cover.
Six
interconnected shipping containers connected by a cold porch walkway
made up the central services part of the camp. The generator room housed
two 75 kVA air cooled generators that provided the electricity
requirements for the camp. One generator could also be used as a
duplicate unit for either the camp or drill site if necessary. Sea water
was desalinised in the plant container with a reverse osmosis system
providing up to 2,000 litres of fresh water per day. The plant room also
housed the waste water discharge system, fresh water filtration, heat
exchangers; a JP8 fuelled boiler and hot water storage.
Three
showers and hand basins were available in the ablutions container with
separate laundry and 4,000 litres of fresh water storage. The kitchen
container was fitted out with cooking facilities to provide meals for
personnel working 12 hour shifts. The sleeping accommodation at the camp
was in electrically heated and insulated 6-berth containers arranged
with 3 containers each sharing a common cold porch.
The science
lab, housed in 2 containers, was the area where the core was logged,
described and then stored until it was transported to the Crary Lab at
McMurdo Station.
Operations
of Science Team at Cape Roberts and at Crary Laboratory, McMurdo Station
The
project thanks the US Office of Polar Programs for the use of Crary
Engineering and Science Center, McMurdo Station, for core analysis.
The science
team were staged to arrive each season when the core was expected, those
with tasks at the drill site or Cape Roberts arriving first. Once coring
and sampling were completed, the focus turned to the production of text
and images for the Initial Report, which was largely completed each
season over a period of 3 weeks following the drilling and before the
science team left the ice. The Initial Reports for each season have been
published around 4 months later in Terra Antartica. Details of how
this work was carried out can be found in these reports.
|